California High-Speed Rail: $126B, Zero Track Laid
California high-speed rail now carries a $126 billion estimate, a $90 billion funding gap, and zero completed track after 16-plus years.
Watch the full episode in the player above — everything in this article comes straight from the episode.
Prefer audio? Listen to the podcast version:
California high-speed rail now carries an estimate of just over $126 billion, sits roughly $90 billion short on financing, and has not completed a single stretch of high-speed track more than 16 years after voters approved it.
Key Takeaways
- Officials now estimate the San Francisco-to-LA line at just over $126 billion, up from a 2008 estimate near $33 billion.
- The project is roughly $90 billion short on financing, and no high-speed track has been completed.
- In 2025, President Trump canceled $4 billion in federal grants; the transportation secretary called it a mismanaged boondoggle.
- The route has been scaled back toward a Bakersfield-to-Merced segment, and it would no longer be truly high-speed.
How much does California high-speed rail cost now?
Officials now estimate the full San Francisco-to-Los Angeles line at just over $126 billion. Voters approved nearly $10 billion in bond funding in 2008 for an 800-mile system then estimated to cost around $33 billion, so the price has roughly quadrupled.
California high-speed rail is a voter-approved bullet train project, launched under Governor Jerry Brown, that has ballooned in cost and stalled in construction for well over a decade. Roughly $20 to $25 billion has been spent so far, according to the episode’s estimate.
Why has no track been laid?
The financing was never fully in place when construction started, and officials have now admitted as much. One official told 60 Minutes the funding was not there to complete the rail when construction began, which the episode compares to pouring a home’s foundation before securing the loan.
Free weekly email
The Friday Reasonable Brief
A short stack of receipts, every Friday. Free.
We never sell your email. Unsubscribe anytime.
We’re now in 2026. There are no trains. There’s no track laid. It was a complete bait and switch.
Officials on the project conceded that “mistakes were made” and that some of the criticism is “very fair,” an extraordinary admission for a public works project of this scale. The initial planning, they acknowledged, was more theoretical than grounded in what could actually be built.
What did the 60 Minutes segment reveal?
The 60 Minutes segment showed forward-facing officials insisting the project can still get done while struggling to answer basic questions about financing. Asked directly whether the funds exist to complete LA to San Francisco, an official conceded the full amount is “not there today.”
Representative Vince Fong called it a complete bait and switch. An older official, asked whether he expected to see the system built in his lifetime, said he was “dubious,” a striking answer from someone who has championed the project. The episode contrasts this with earlier coverage of the rail’s mounting crisis.
Did the federal government pull funding?
Yes. In 2025, President Trump canceled $4 billion in federal grants for the train, and Transportation Secretary Sean Duffy declined to release additional Federal Railroad Administration funding.
Duffy said the administration favors high-speed rail in principle but that this project “wasted billions in taxpayer dollars, yet delivered nothing.” Citing 16 years of failure, no completed high-speed track, and escalating costs, he labeled it a mismanaged and over-budget boondoggle. The episode compares the federal role to a construction lender refusing a draw because there is no completed work to inspect.
What happens to California high-speed rail now?
The project is being scaled back and is hunting for private investors to cover the gap. The route has shrunk toward a Bakersfield-to-Merced segment, roughly a third of the original distance, and officials talk of “optimizing” it, which in practice appears to mean shorter and slower.
The core problem is that a project of this size was designed and managed largely by politicians rather than by engineers working from firm land acquisition, eminent domain, and financing plans. The episode’s blunt verdict: if this were a private business, it would have gone bankrupt decades ago. The same pattern of failed fiscal planning shows up in Washington’s $9 billion tax hike.
Can California high-speed rail be finished without federal money?
Officials claim the initial segment can be, but they concede the full 494-mile buildout would be, in their own words, challenging without federal help. With roughly $90 billion still unfunded, the state is now courting private investors to close the gap.
The pitch is a hard sell: a project decades in the making, scaled back to a Bakersfield-to-Merced stretch, no longer truly high-speed, with no completed track to show. An 80-year-old official on the project said he was dubious he would see the full system built in his lifetime.
Frequently Asked Questions
How much is California high-speed rail estimated to cost?
Officials now estimate the San Francisco-to-LA line at just over $126 billion, up from a 2008 estimate near $33 billion, with roughly $90 billion still unfunded.
Has any high-speed track been completed?
No. According to the episode and the 60 Minutes segment, no high-speed track has been completed after more than 16 years, despite an estimated $20 to $25 billion already spent.
Why did the federal government cancel funding?
Transportation Secretary Sean Duffy cited 16 years of failure, no completed high-speed track, and escalating costs, calling the project a mismanaged and over-budget boondoggle, and $4 billion in federal grants was canceled.
When the officials running a project admit the money was never there and the track still is not laid after 16 years, at what point should a state cut its losses? Weigh in below.
Full Episode Transcript
Read the full transcript of this episode
Just to be clear, as we speak right now, are the funds there to complete LA to San Francisco? >> The entire amount of money we need, not there today. But do we believe we can get those funds to get the the project done? Absolutely. How much do you estimate it’s going to cost to connect high-speed rail San Francisco to LA? Today, we estimate, with the right optimization, just over $125 billion. I think $126 billion is the current estimate for that. >> This is not just a transportation project. This is about reimagining the future of this region. >> Meanwhile, in 2025, President Trump canceled $4 billion in federal grants for the train, swiping at a political nemesis in the process.
Did you ever hear of Gavin Newsom? He has got that train is the worst cost overrun I’ve ever seen. In a statement to 60 Minutes, Secretary of Transportation Sean Duffy said the administration is in favor of high-speed rail, but this project has, quote, wasted billions in taxpayer dollars, yet delivered nothing. Can this be done without help from the federal government? This initial segment, we believe so. The ultimate 494 miles of building this out without the federal government’s help will be challenging. There’s no doubt about that. Is this a non-starter to build a project like this without federal funding?
Well, not only can it be done, it shouldn’t be done. Uh, because a lot of the benefits of the project, the reason why you build a project is public. So, the reality of the high-speed bullet train from San Francisco to Los Angeles is so, literally, literally off track. Not even off track, because off track would indicate that there is track there. This has been literally decades with nothing going on. Now, we’re up to $126 billion. We’re shy 90 billion dollars in financing. The federal government has pulled back 4 billion in recent funding, and it’s gotten so bad that the This is Those were 60 Minutes clips you just saw.
And basically, the forward-facing public officials for the light rail light light rail project are saying, “Oh, yeah. Oh, yeah. We we can get her done.” You see them kind of looking around, and you see the interviewer going, “What are you talking about?” Because the numbers are so preposterous. They’re so crazy that this this this will not get built in my lifetime. I’m 57. There’s no way this gets built. There There’s no way moving forward. This is just going to get absolutely spun out, spun out. “Oh, yeah, we can do it.” They’re now looking for private investors to fund this bad boy. Hey, I got a deal for you.
Let me pitch you on a high-speed light rail that initially went from LA to San Fran. Now it’s down to Bakersfield to Merced. I know that’s that’s about a third of the distance we were talking about. It’s no longer going to be high-speed. It’s going to be slow-speed. And no, no, we’ve been you know, we’ve been working on this since like the late ’90s, and we had funding in place for like, you know, 8 billion back in 2008. Um but yeah, we got real real Honestly, we got nothing. We we got, you know, parcels of land kind of worked up. Eminent domain? I mean, sort of. Have we actually built a single rail on this bad boy?
No. The answer is no. Who’s going to want to Who’s going to want to fund that? What kind of nut job is going to say, “Yeah, let’s do this. This is going to be the greatest thing ever.” Nobody. Let’s check this article out by Fox. California’s high-speed rail fiasco exposed in brutal 60 Minutes segment. It It is It’s brutal. It’s It’s absolutely brutal. State officials admit mistakes were made. I love I love the intro where he’s like, “Yeah, you know, the the public should have been probably We should have been more should have disclosed to the public kind of what the deal was. And these guys literally come out and say, “The initial planning and the initial concept behind this light rail was more theoretical than reality.
If you’re any kind of an engineer, do you deal in theoretical or do you deal in this is what we can do, this is what we can uh build, this is what we can accomplish right now today because everything else is just nonsense. It’s just nonsense. Hey, we’d like it to go from the moon to Pluto. That’s not really feasible, so let’s do this instead.” Right? I I mean, uh what are we even doing? State officials admit mistakes made as stalled project faces potential $125 billion price tag. Who in the world is going to step in and say, “Yeah, yeah, let’s fund this.” It’s certainly not Trump. Now, I think some of um the There’s a lot of politicking going on here, right?
Trump hates Newsom. Newsom spends his whole day focused on Trump Derangement Syndrome. I don’t really think it’s helping his career because I don’t look at a guy and say, “That guy makes fun of that guy really well, so I’m going to vote for him.” You know, I I think there is this belief that if you make enough fun of Trump, somebody’s going to elect to But it’s projects like these that Trump and I I don’t I don’t I don’t condone calling Newsom News scum. You know what I mean? I mean all you got to do is point out clearly the obvious about California and you don’t have to step down to Newsom. It is funny.
I I got to admit it is funny. It’s a it’s a funny play on words, right? It’s the guy’s name Newsom. But that interview with Newsom’s I’m sorry, Newsom’s wife. She’s talking about just absolutely getting rid of free speech if women were the leaders of high-tech, women were leaders of social media, we wouldn’t have any more bullying and making people feel bad. You know that half the fun of in the internet is just making fun of other people that you don’t agree with. I mean that’s it’s kind of what it’s all about, right? It’s it’s like yeah, this is what we’re doing. That’s a terrible idea. Here’s why.
And we can agree to disagree. I think you’re absolutely effed in the head for voting that law in, but you know what? It’s America. See, you can do what you want. I’m just not going to stick around to find out how it goes. CBS News 60 Minutes targeted California when CBS when CBS figures it out. That is that is that’s the benchmark. That’s the bar, right? Oh, CBS has got this down? Huh, it must be true, right? Targeted California’s high-speed rail project on Sunday speaking to multiple officials about the project that has yielded little return since state residents voted in support of it in 2008.
We didn’t see anything, but um Representative Vince Fong, he had a great segment in that. Check out that that 60 Minutes segment. It’s I don’t a lot of 60 Minutes stuff is like what? It’s so biased. No. No. But it it was a great interview. Um We’re now in 2026. There are no trains. There’s no track laid. It was a complete bait and switch,” Fong told 60 Minutes. 100%. I’ve only been following this for since I got really got into podcasting cuz I’m not from California. I don’t really care if there’s a light rail that goes from LA to San Fran. The more I think about it, yeah, that would be cool. But that’s in theory.
The billions of dollars it’s going to take to put this together and how much has already been spent and the reality that this is never going to be completed and some projects are just doomed from the start. You know what I mean? Like you just you shouldn’t undertake it. This is one of those, especially in California, because politicians in California, so many of them are ideal-based and that doesn’t that doesn’t really convert to reality, which is, can we get this done? Uh from my understanding and my uh research, a lot of the issues have come from the fact that before you get this kind of project lined up, you got to kind of get the headwinds of how your land acquisition is going to go, how your eminent domain is going to go, how are you going to be able to fund it, how are you going to be able to put it together.
And yes, there have been cost overruns, things, you know, inflation, that kind of stuff. Okay. But to literally go quadruple on the budget and have nothing really to show for it to me is astounding. And I don’t think Trump is wrong saying this is the worst cost overrun he’s seen. How many projects do you know that quadruple in billions the cost to construct? You know what I mean? Big commercial projects, big skyscrapers, uh you know, 90 billion lacking in financing? No, it just doesn’t happen. But this bad boy is such a massive, massive project. And it’s it’s being designed and and built by people in California that are like, “Ah, I think we can get it done.” And then the reality is, “Mhm, it doesn’t look so, guys.
Maybe we need to put away that shovel and put away that hammer and put away that jackhammer and call her good. Just call her good.” Got how many billion? 20 billion invested so far? 25 billion? Something like that? So far money spent, you know what? Let’s just back out. California voters approved nearly 10 billion in taxpayers funds in muni bonds. 800-mile high-speed rail system. And um which was estimated to cost in 2008, I believe, 33 billion. Now we’re at 126 and counting. What about the statement that the one dude being interviewed said, “If we optimize this project.” What are you talking?
What does that mean? Does that mean make it smaller? Make it slower? We’re going to optimize it. It’s like your It’s like your dishwasher. These new dishwashers take over 2 hours because they heat the water up to just barely lukewarm so that lots of energy isn’t spent. I’ll tell you what. I want my dishwasher to be hot. I want it to kill that bacteria. I don’t really care that it’s energy efficient. It’s a dishwasher. You know what I mean? It’s like, “Oh, but if all the dishwashers in the world were high in efficient.” Don’t care. Why am I spending energy running my dishwasher for 2 and 1/2 hours on a normal cycle?
It’s crazy. It’s nuts. Maybe some you know, engineer, “Oh, Shawn, you’re backwards on that one.” Okay, yeah, I don’t care. I just I I don’t want to go to a movie, come back and my dishwasher’s still running, you know what I mean? It’s like, “What? What are we doing?” The project, which began under former Democratic Governor Jerry Brown, uh has been plagued by ballooning costs and delays. Latest estimate, 125 billion and change. So bad. So bad. I mean, this is this is one of those projects that again will derail Governor Newsom, Newsome’s political ambitions in 2028. This is on part of This is on his watch.
He didn’t start it, but he’s definitely been Oh, we need this. In order to have this kind of vision, you need to think big, right? Got to think anyway, you might as well think big. Yeah. Part of the deal, right? California High-Speed Rail Authority said it expects trains to begin running in 2030. Let’s see. It is now 2026, and you haven’t completed a damn segment of it, but you’re going to without federal funding? Without federal funding, you’re going to do this without federal funding. Oh, yeah. Yeah, we’re going to do some We’re going to We’re going to reduce the cost. We’re going to get some private funding.
And what else was the other thing in there? Oh, we’re going to optimize it or whatever they’re doing. Absolutely nutty. CBS reported the state was getting ready to lay down track for the project, but instead of LA to San Fran, uh got to We got to cut We got to We got to We got to optimize this just a scooch. Used to be this long, now it’s this long. It’s going to cost less. he’s one of the officials we heard from, acknowledged that mistakes were made in the project. See how how many billion over cost are we? You got nothing. You got no funding. And your outlook is you got nothing. You’ve literally got nothing.
Mistakes were made in the project. And that And And that And that is a massive massive revelation, right? Oh, mistake mistakes were made. Huh, okay. All right. The fact that officials on this project are coming out and saying this kind of thing, because the running joke has been it’s been so obvious for so long that this is just an absolute cluster from the get-go. This has been on on sandy unstable using construction terms now uh ground. It’s It’s It’s It’s wildly unstable. You can’t build on it. It can’t be built. And here we are. Well, we’ve got some mistakes. Mistakes have been made. We made some mistake Yeah, hm yeah, and you got no project.
There were mistakes made. Some of the criticism on this project, I think, is very fair. Oh, that is classic. I think is very fair. Well, they don’t have a choice. It This project is so bad. It’s so upside down as far as taxpayer dollars being spent on something just that that from the get-go has been doomed. It should It should been doomed. It’s the project that’s never really going to take off. I don’t think the voters fully understood. Now, let’s blame it on the voters, right? Let’s blame it on the voters. I don’t think the voters fully understood. Well, how could they? Voters don’t typically Yeah, I think I’ll build a $126 billion train to nowhere today.
Let me get out my Let me get out my cell phone and we’ll just ask Perplexity how to do that and then I’ll you know, get out that shovel and jackhammer I talked about earlier and you know, maybe a a bag of quick rate or something and we’ll get going. We’ll get this bad boy and you know, going. We’re put my hard hat in on from from Home Depot. Let’s make this up Let’s make this happen. The voters didn’t fully understand because the people planning this, designing it, and engineering it didn’t fully understand. This has been the blind leading the blind, right? You’ve literally got Jeff and Mutt running this show.
And he just you’re left with oh, okay. So, now here’s what we’re going to now. The truth. I don’t think the voters fully understood and neither did we in the public sector what it was going on to take to actually get this project delivered. Okay. All right. If this were the first high-speed bullet train to nowhere ever completed or ever, you know, thrown out there to be built, then I would say, all right. Okay. So, you just didn’t really, you know, it’s like going to the moon. What’s it going to take? It’s if we went to the moon. Going to the moon, if we went to the moon, what’s, you know, how you going to get there?
All right. You know, that first time, too, you’re going to have some issues. But, there are these projects all around the world. There are many other countries where you just hop on a train and couple hundred miles an hour, boom, you’re there, right? They’ve made an effort to to do this kind of project and they’ve undertaken them and they haven’t done, you know, massive over over-budget uh type type scenarios. They’ve they’ve Yeah. But, this is California, right? And because this is California, it’s led by a bunch of Democrats and this is what you get. This is where you’re at. Such a big project that has gone absolutely sideways.
Williams told CBS that the financing was not there to complete the rail when construction started. That’s like a a a a homeowner that’s going to build a proposed home. Um so, you got all your financing in place? No. Well, let’s go ahead and pour that foundation. Let’s get the excavation done. Let’s get that foundation poured and then we’ll we’ll figure it out from there. We’ll work it out from there. Well, who’s going to lend you money to do the foundation? I I don’t know. You know, we’ll work it out. We’ll we’ll get it together. And we’ll do a little out of pocket. And that’s literally what you’ve got, money that’s already been spent, the billions of dollars already spent.
Is California’s money, federal government’s money, your and my money, taxpayers’ money? It’s like a sunk It’s like a sunk project, right? You need to just It’s like one of my jet skis. We just need to take it out in the middle of Lake Washington and sink it. Yeah. Yeah, we do. It wasn’t Let’s be real. We had a lot to learn. We had a lot of growth to do. And you know, it’s arguable whether we should have been clearer about that. You started building a project you had no business building. You didn’t have everything lined up ahead of time. You didn’t do this so I’m and I am no engineer. But I think there it was one of those yeah, yeah, this is This could be the greatest thing ever.
Oh, this is the best. And then here we are. Yeah, 18 years later and you got nothing. I shouldn’t say nothing. You’ve got bits and pieces of progress. But it was supposed to be done 6 years ago. It was supposed to be done in 2020 and it’s it’s not even it’s not even remotely close. Thompson was asked by CBS if he thought he’d seen the system built in their lifetimes. This is the older gentleman he was talking to. I don’t know. I’m dubious. I’m dubious. I think he’s like 80 81. Absent a national political will to work with the states to create some of these systems, I think it’s going to be in, of course, my lifetime, almost certainly not.
Fair enough. Guy’s 80. Is it going to be built in the next Call it 20 years? No. Not even close. Haven’t even gotten close to completing it. But maybe yours, he’s telling the interviewer, I don’t know. And the interviewer is probably, I don’t know, 40s, maybe 50-ish, not 30s, not 60s, somewhere in there, right? California’s high-speed rail project suffered a major setback. Sean Duffy, transportation secretary, said, “No, we are not giving you any more money. The $4 billion? No.” And unspent federal funding by the Federal Railroad Administration, “No, we’re not moving forward with that. You guys can stick it.” Because the the results haven’t been there.
It’s like a draw. You know, when a a builder is building a home and they get a draw for the amount that they’ve already constructed, say it’s at frame. They’ve had a draw for their you know, their concrete, their flatwork, their excavation, all that. A lot of times you pay for that out of pocket. And then you get to the point where you’ve got a a draw for maybe your your framing draw. You know, somewhere along that and then you’ve built part of it and you get paid for part of it. So, that’s how the the loan the loan goes. It’s a construction loan. Well, federal government’s funding a portion of this and they said, “Yeah, uh no.
You’re not getting a draw cuz you got nothing for us to look at as far as progress goes. We’re the lender on the project. We’re a lender, a partner lender, and we’re going to say, uh no.” Fair enough. I mean, that’s what would happen in the real world. No, we’re not we’re not we’re not sinking any more of the taxpayers money into this ridiculous, absurd project. You guys are going to have to go fly a kite cuz that’s maybe what you’re capable of, right? Citing 16 years of failure, no completed high-speed track, and escalating costs. Well, that that’s fair enough, isn’t it? I mean, you want to say, “Well, this is political games being played here.” No, this is reality just being identified.
16 years, no completed high-speed track, escalating costs. Duffy declared the project at the time, dubbed the train to nowhere, a mismanaged and over-budget boondoggle. And that’s what it is. It’s a boondoggle. It’s a wild, wild boondoggle. I mean, and I would I was texting with somebody, one of you guys that watches all the time, and you were saying, “It’s the gift that keeps giving to podcasters like me.” Because, you know, right now with with with what’s going on in Washington state, you know, what’s happening with Oregon, what’s happening with parts of California, this being a California story, you almost think that forces are at play to basically absolutely tear apart and destroy the entire West Coast to to make it just easier to control.
I mean, and I I think I think this this high-speed rail to nowhere, this is this is just indicative of how planning, how construction, and how a reality meets ideology in a state like California, which has had basically Democrat supermajority for long, long time. And this is indicative of failed ideology, failed methodology, failed planning, failed financing. If this were a business, this would have been broke decades ago. And would have been bankrupt, and would have been gone, and nobody would have funded it. But because it’s this kind of cool idea, hey, you ever been to another country? You ever rode the, you know, high-speed bullet train, whatever it is, in whatever country?
You ever read wrote that? Well, yeah, you’re not going to ride that in California anytime soon, either. Cuz it’s not there. Cuz it’s a bankrupt idea that’s probably never going to happen. If this thing if this thing happens, I’ll be like 85 years old going, “Remember back when I was less than 60 years old, we talked about this never happening?” And I you know, I I won’t know which way is up and down uh when I’m you know, like 90. Hey, they finally built it. It’s now only two and a half trillion dollars, but they did it. They did it. How many podcasts am I going to have on this by then? A lot. Does this literally does this literally just get the axe?
Do they axe this? Do they just cut their losses? No, they can’t. They There’s no way they can. There’s no way they can’t. Politician every now and then is just going to jump up and say, “Oh, we’ve got to do this for the future of mankind in California.” Anyway, glass half full podcast, days, weeks, months, years, decades. Decades. That’s the That’s the kind of content California’s given me. Washington State’s given me. Seattle’s given me. Portland’s given me. It’s great. Thanks so much for being here. Love to have you subscribe. Hit that notification bell. I’ll see you in the next episode. Bye for now.
Up next

Newsom Homelessness Spending Record Becomes GOP’s 2028 Target
Watch next


Topics in this story
See more stories on each topic, and what people are saying about them.
Your host
Sean Reynolds
Sean hosts ReasonableTV: independent, receipts-first news on Seattle, Portland, California and the companies that shape them. The daily show reaches 189,000 YouTube subscribers.
Reasonable+
The stories too hot for the algorithm.
$3.33 a month, billed $39.99 a year (2 months free) — or $3.99 month to month.
Start your 14-day free trialYour daily show stays free. Cancel anytime during the trial and you pay nothing.
Join the conversation
Keep it factual. No insults. House rules
No comments yet. Start the conversation.